October 15, 2026
"That can go either way," Ray Biggs of the Maryland Transit Administration told the Montgomery County Council's Transportation and Environment Committee about the Purple Line's opening, according to Bethesda Magazine's republication of WTOP's report on October 6, 2026. Committee Chair Evan Glass had just asked him if April 2028 was the more realistic date. Biggs said the contractual date "does remain December 30, 2027," and called the final timing "dynamic," depending on safety testing.
Five days earlier, the Montgomery County Planning Board voted to move a second timeline forward. That one covers the rules for what can be built on the lots around the stations at Manchester Place, Long Branch and Piney Branch Road. Anyone pricing a home in eastern Silver Spring right now is pricing both timelines, and neither one is fixed.
The county's own feasibility research found that new zoning is unlikely to set off widespread redevelopment of the area's existing apartments under current market conditions. Most of the housing near a station today is likely to still be there when the train starts running.
The physical project is close to finished. The MTA reported on September 3, 2026 that construction was 92% complete and vehicle testing was running on more than half of the 16-mile alignment. The schedule on the project's official progress page still shows passenger service as "Winter 2027," with end-to-end system training in Spring 2027.
| Date | Milestone | Source |
|---|---|---|
| July 16, 2026 | Live-wire testing begins between the Lyttonsville facility and Bethesda; all track installed | MTA |
| September 2026 | Live-wire testing reaches more than 70% of the alignment | Purple Line newsletter |
| October 11, 2026 | Spring Street Bridge downtown described as "substantially complete" | Source of the Spring |
| Oct. 25 – Nov. 6, 2026 | Overnight overhead-wire work on Wayne Avenue between Dale Drive and Manchester Road | Purple Line updates |
| December 30, 2027 | Contractual opening date | Bethesda Magazine |
Station work in the eastern stretch is still underway. The official updates page lists ongoing utility and track work at the Long Branch and Manchester Place stations, including work in the Plymouth Tunnel. April 2028 came up at the October hearing as a possible date. It was raised as a question, though, not adopted as a new forecast. A buyer who expects to commute on the line should plan around a window, since no single date is set.
The Eastern Silver Spring Communities Plan is the master plan for the area between Sligo Creek, the Capital Beltway and the Prince George's County line. On October 1, the Planning Board accepted the Working Draft as the Public Hearing Draft, and it set hearings for January 7 and January 14, 2027.
For someone buying a detached house, the key recommendation covers single-family lots within a quarter mile of a Purple Line station or within one block of Colesville Road, University Boulevard or New Hampshire Avenue. The draft would rezone those lots from R-60 to Commercial Residential Neighborhood, or CRN. Lots beyond those distances would keep their current R-40, R-60 or R-90 zoning. What the new zoning would allow depends on which street the lot faces. The September 24, 2026 staff report lays it out this way:
| Lots facing a main corridor | Lots facing a neighborhood street | |
|---|---|---|
| Height limit | 45 feet | 40 feet |
| Building types | Single family, duplex, triplex, townhouse, small apartment building | Single family, duplex, triplex |
| Front setback | 0 to 15 feet | 20 feet |
| Maximum site coverage | 50% | 35% |
| Lot consolidation | Not allowed | Not allowed |
Several of these limits are new since the preliminary recommendations. The staff report says heights were cut by five feet. Projects over 10,000 square feet now need site plan approval. Projects of three or more units would have to include at least 15% workforce housing units or pay into the Housing Initiative Fund. The setbacks, coverage limits and the ban on combining lots sit in a separate overlay zone. That overlay needs its own approval after the plan is adopted, including review by the Planning Board and County Council with public comment.
The draft also changed at one well-known site. At the Silver Spring YMCA property near Indian Spring, it lowered the recommended maximum height from 120 feet to 60 feet and the floor area ratio from 2.0 to 1.25.
The usual story is that a train plus upzoning brings a wave of new buildings around the stations. The plan's housing appendix doesn't support that story. A redevelopment feasibility analysis in Appendix F, which cites a July 17, 2026 report from the National Center for Smart Growth, tested whether existing apartment communities in the plan area could be redeveloped. It found redevelopment "unlikely under today's market conditions." That held even when the model assumed much higher density, much higher rents or lower construction costs. The only scenario that looked potentially viable was a Low-Income Housing Tax Credit rehabilitation, which renovates buildings instead of replacing them.
The planners say plainly what that means. Their report says "additional density alone is unlikely to trigger widespread redevelopment," and that preservation and reinvestment "remain the most likely outcome for many existing apartment communities today." The plan's FAQ says the same about houses. A zoning change "does NOT tear anything down," and existing buildings stay as they are unless an owner chooses to redevelop.
Put those findings next to the no-consolidation rule and the likely pace of change becomes clear. Builders could not combine several lots into one larger site. So any new duplexes or triplexes on neighborhood streets would come one lot at a time, when an individual owner decides to build. The housing itself is old. The appendix reports that 55% of the plan area's housing was built before 1960. When the train opens, most of the homes and apartments within a quarter mile of these stations will likely be the same buildings standing there today.
In July 2026, Bethesda Magazine reported that the Planning Board approved Sonina Properties' plan for a 148-apartment building at 831 University Boulevard East in Long Branch, between the future Takoma Langley and Piney Branch stations. About 26 of the units are moderately priced dwelling units, and the developer expects construction to start in early 2027. With construction starting in early 2027, the building's completion and the line's opening window could fall close together.
Long Branch's commercial core is not part of the rezoning. Its commercial properties keep the CRT zoning adopted in the 2013 Long Branch Sector Plan. That area includes the Flower Shopping Center and the historic Flower Theater, which Bethesda Magazine's June explainer named in its coverage of the plan. In the preliminary recommendations, planners proposed supporting the Long Branch Business League and offering incentives to help local small businesses stay or relocate nearby, as The MoCo Show summarized in March.
Some buyers will want to know how much the train is already worth in a home's price. The sources here don't give a station-level figure. A 2024 study by Nicholas Finio summarizes earlier research that found prices rising ahead of the line for single-family homes and multifamily rents along the corridor. The passage gives no size for that effect.
The broader numbers describe a county market that is steady, with a little more supply. In August 2026, Montgomery County's median sold price was $640,000, up 3.8% from a year earlier. Median days on market were 15, compared with 16 a year before. Sales fell 11.3% to 779 homes, and the county had 2,032 active listings, or 2.5 months of inventory, according to Maryland REALTORS' August 2026 report. Greater Capital Area Association of REALTORS figures for July 2026, reported by The MoCo Show, showed a $656,000 median, down 0.6% from a year earlier. Average days on market were 30, eight more than the year before, and new listings were up 5.1%. One series reports the median days on market and the other the average, so the two figures measure different things.
These numbers cover the whole county. They can't separate a house a quarter mile from Manchester Place from one across the Beltway. So the price of a near-station home has to be judged from comparable sales on nearby streets, the proposed zoning on that block and a realistic idea of when the train will run.
Does the rezoning change my house if I buy within a quarter mile of a station? No. According to Montgomery Planning, rezoning only updates what an owner may build in the future. Existing homes stay as they are unless their owner chooses to redevelop.
Where can I check a specific property? Montgomery Planning publishes an interactive zoning map with recommendations for each property.
Is the zoning final? No. The plan is a Public Hearing Draft with hearings set for January 7 and 14, 2027, and the overlay zone needs its own approval after the plan is adopted.
If you're weighing a home near Manchester Place, Long Branch or Piney Branch Road, The Guzzone Group of Compass can help you check where it falls on the draft zoning map and line up its price against the Purple Line's realistic opening window. Start with a complimentary home strategy call.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.
Stay up to date on the latest real estate trends.
We embrace people of all walks of life, always approaching new clients and different circumstances with empathy and compassion.